Project Scope:
PGSR was engaged directly by QAL to provide all trade, non-trade, tooling and equipment resources to execute the minor outage works on QAL Turbine and Generator overhaul work.
Specific works included:
- Turbine disassembly, detailed inspection and reassembly
- Emergency stop valve and control valve overhauls
- Generator disassembly, detailed inspection and reassembly
- Overhaul of Turbine and Generator auxiliary equipment including oil pumps, steam condenser and control devices
Customer Details:
Queensland Alumina Limited
Project Duration:
8 Weeks - Dayshift - 60hr / weeks
Resources provided:
Site Crew - All Trades & Supervision - 550hrs
Tooling provided:
1x 20 Ft tooling container & Specialised tooling included Knaack box tooling, Turbine rotor rollers, Main stop valve clamping table, Vacuum pump, Oil purifier unit