Project Scope:

PGSR was engaged to provide project/site management, supervision, trades and non-trades to execute the minor outage works on the Muja M5 and M6 Units.

Specific works included;

  • Pedestal Bearing Inspections
  • Inspect and report on ESV valves
  • M6 LP Blade Inspection
  • M5 H2 Cooler Inspection

Customer Details:
Toshiba/Synergy

Project Duration:
8 weeks - Dayshift - 60hr/weeks

Resources provided:
Site/Project Management & Full Crew - 5500hrs

Tooling provided:
One 20ft Specialised & General Tooling Container