Mount Piper Unit 1 Steam Turbine Upgrade – October 2020

Mount Piper Unit 1 Steam Turbine Upgrade – October 2020

Project Scope:

PGSR was engaged to provide all supervision, trades, non-trades and HSE resources to execute the major outage works on the Mount Piper upgrade project. 

Image features CV Rotable spare being lifted in.

Specific works included:

  • Replacement of 660MW turbine steam path 
  • Generator stator rewind
  • LP heater replacement
  • Turbine steam valve overhaul
  • STG auxiliary and cooling water system maintenance

Customer Details:
Toshiba / Energy Australia

Project Duration:
10 weeks – 2 shifts – 60hrs/week

Resources provided:
50 – 50,000 man-hours in total

Tooling provided:
Six tooling containers including the tooling serving container