Mount Piper Unit 1 Steam Turbine Upgrade – October 2020
Mount Piper Unit 1 Steam Turbine Upgrade – October 2020
Project Scope:
PGSR was engaged to provide all supervision, trades, non-trades and HSE resources to execute the major outage works on the Mount Piper upgrade project.
Image features CV Rotable spare being lifted in.
Specific works included:
- Replacement of 660MW turbine steam path
- Generator stator rewind
- LP heater replacement
- Turbine steam valve overhaul
- STG auxiliary and cooling water system maintenance
Customer Details:
Toshiba / Energy Australia
Project Duration:
10 weeks – 2 shifts – 60hrs/week
Resources provided:
50 – 50,000 man-hours in total
Tooling provided:
Six tooling containers including the tooling serving container