Jeeralang B1 Gas Turbine & Generator Overhaul

Jeeralang B1 Gas Turbine & Generator Overhaul

Project Scope:

PGSR was engaged to provide all trades and non-trades resources to execute the major outage works on the Jeeralang B1 gas turbine and generator.

Specific Works included;

  • GT rotor removal and bucket replacement
  • Replacement of GT nozzles and shrouds
  • Generator rotor removal and retaining ring replacement
  • Assembly followed by cold and hot commissioning

Customer Details:
Toshiba / Energy Australia

Project Duration:
30 weeks – 60hrs/week

Resources provided:
Average 8 – 14,288 man-hours in total

Tooling provided:
One tooling container — for general tooling and rigging