Eraring Unit 1 Major Outage
Eraring Unit 1 Major Outage
Project Scope:
PGSR was engaged directly by Toshiba to provide labour and tooling / equipment resources to execute the Major Outage works on Unit 1 located at Eraring Lake Macquarie NSW.
Customer Details:
Toshiba / Origin Energy
Project Duration:
14 Weeks of Dayshift / 10 weeks of Nightshift - 60hr/weeks
Resources provided:
Site Crew - All Trades & Supervision - 1680hrs
Tooling provided:
1 x 20 FT Consumables container, 1 x 20 FT Rigging container, 2x 20 FT General tooling containers, 1 x 10 FT generator tooling container & Specialised tooling ,