Darling Downs Power Station Valves Inspection
Darling Downs Power Station Valves Inspection
Project Scope:
PGSR Provide Labour and Tooling to perform 2 x Combined MSCV valve disassembly, inspection and re-assembly. Remedial works lapping / valve bush / stem honing and additional works.
Customer Details:
Toshiba / Origin
Project Duration:
3 Weeks - Day Shift - 60hr / weeks
Resources provided:
Site Crew - All Trades & Supervision - 1080hrs
Tooling provided:
2 x Knaack Boxes of Specialised & General Tooling / Rigging Equipment