Darling Downs Power Station Valves Inspection

Darling Downs Power Station Valves Inspection

Project Scope:

PGSR Provide Labour and Tooling to perform 2 x Combined MSCV valve disassembly, inspection and re-assembly. Remedial works lapping / valve bush / stem honing and additional works.

Customer Details:
Toshiba / Origin

Project Duration:
3 Weeks - Day Shift - 60hr / weeks

Resources provided:
Site Crew - All Trades & Supervision - 1080hrs

Tooling provided:
2 x Knaack Boxes of Specialised & General Tooling / Rigging Equipment