Bayswater Unit 4 Steam Turbine Upgrade – March 2020

Bayswater Unit 4 Steam Turbine Upgrade – March 2020

Project Scope:

PGSR was engaged to provide all supervision, trades, non-trades and HSE resources to execute the major outage works on the Bayswater upgrade project.

Specific works included;

  • Replacement of 660MW turbine steam path
  • Generator stator rewind
  • Turbine steam valve overhaul
  • STG auxiliary and cooling water system maintenance

Customer Details:
Toshiba / AGL

Project Duration:
10 weeks – 2 shifts – 60hrs/week

Resources provided:
60 – 60,000 man-hours in total

Tooling provided:
Eight tooling containers including the tooling serving container