Bayswater Transformer Maintenance
Bayswater Transformer Maintenance
Project Scope:
PGSR were engaged to provide labour and tooling for the transformer maintenance at Bayswater power station
Customer Details:
Toshiba / AGL
Project Duration:
10 Weeks - Dayshift - 60hr / weeks
Resources provided:
Site Crew - Specialised Fitters, Mechanical Fitters, Advanced Riggers and Trade Assistants - 6600hrs
Tooling provided:
2 x Transformer containers, specialised tooling and consumables & PPE Requirements