Jeeralang B3 Major Turbine and Generator Outage
Jeeralang B3 Major Turbine and Generator Outage
Project Scope:
PGSR has been invited back to Jeeralang to engaged to provide all trades, non-trades and supervisory resources to execute the major outage works on the Jeeralang B3 gas turbine and Generator.
Customer Details:
Toshiba/Energy Australia
Project Duration:
12 weeks - Dayshift & Nightshift - 60hr/weeks
Resources provided:
Site/Project Management & Full Crew Day & Critical Path Crew Night - 17000hrs
Tooling provided:
2 x 20ft Specialised & General Tooling Container